Sellwood Bridge completes huge milestone: Multnomah County re-opens span ahead of schedule
The temporary Sellwood Bridge is now open for traffic after a 6-day closure allowed workers to move a large portion of the span to make way for construction on the replacement bridge.
On Wednesday, Jan. 23, the first vehicles began crossing the bridge, ending a few days of detours. The temporary bridge opened to traffic 15 hours ahead of schedule. Multnomah County Commissioner Deborah Kafoury was in the first car to cross the bridge after it reopened. βIt feels a lot like the old bridge did, but the new sections seem sturdier,β she said.
On Saturday, Jan. 19, workers began moving the 1,100-foot truss span of the 87-year-old bridge to the north onto new piers. It took 14 hours to move the span, which will create a detour bridge to make way for construction of the replacement bridge.
The truss span was the longest structure ever moved by specialty firm Omega Morgan of Hillsboro. While exact comparisons to other bridge moves are hard to find, experts say the Sellwood truss span was one the longest, oldest bridge sections ever moved in one piece.
Contractors moved the 3,400-ton truss span by pushing it with hydraulic jacks on rails along beams that linked the old piers with the new detour bridge piers. The process was a slow one, with workers moving the span a few inches at a time and then taking measurements to ensure it was properly positioned.
The big move was watched by hundreds of onlookers on the east and west banks of the river. Neighbors near the bridge hosted deck parties and Sellwood areas businesses sponsored a celebration with live music and free buttons that read βI Was Moved! Sellwood Bridge Jan. 2013.β
The detour bridge will minimize the impact of construction on local businesses and bridge users. It provides the following advantages over the original plan to build the new bridge in two phases:
- Savings of $5 to $10 million in project costs
- Reduction of construction time by one year
- Improved safety by separating traffic from bridge construction
- Reduced environmental impacts (due to less in-water work)
"We're continuing to make progress in completing this major transportation project," said Multnomah County Chair Jeff Cogen. "Watching the bridge move was an amazing moment. I'm very proud of the team that pulled off this engineering feat."
The old Sellwood Bridge, which in its former state was ranked a mere 2 on a scale of 0 to 100 on a sufficiency scale, was not built to withstand a major earthquake and had problematic cracks in the west approach. The new portions of the detour bridge have more seismic strength and the old west approach is not part of the detour bridge.
The permanent, replacement bridge is expected to open by the summer of 2015. For more information, visit www.sellwoodbridge.org.
Click here to view a 38-second time-lapse video of the Sellwood Bridge move
News coverage
Watch Portland Move an Entire Bridge in One Day
By John Metcalfe, The Atlantic Monthly - January 23, 2013
By Dana Tims, The Oregonian - January 22, 2013
Multnomah County On Track To Reopen Sellwood Bridge By Thursday
OPB - January 22, 2013
iReport, CNN - January 21, 2013
Crews say Sellwood Bridge project going well
By Keely Chalmers, KGW - January 21, 2013
Omega Morgan boosts credentials after successful Sellwood Bridge move
By Fenit Nirappil, The Oregonian - January 21, 2013
Timelapse video: The Sellwood Bridge's big move
By FOX 12 Webstaff - January 20, 2013
Sellwood Bridge move comes off without a hitch, amazing hundreds of onlookers
By Dana Tims, The Oregonian - January 19, 2013
Sellwood Bridge makes its move Saturday
By KGW staff - January 19, 2013
Engineers Push Sellwood Bridge Onto Temporary Pilings
OPB - January 19, 2013
Inch-by-inch, the Sellwood Bridge is moved
Jennifer Meacham, KOIN Local 6 - January 19, 2013
Sellwood Bridge move with old piers at right
By Associated Press and KATU.com Staff - January 19, 2013